10 JulCentral Valley Expressway Bridge Ribbon Cutting

The Central Valley Expressway (Highway 16 Extension Project) at dusk. April 29th, 2014

Please join us for the Central Valley Expressway Bridge Ribbon Cutting Friday, August 15th, 2014 10:16 a.m. Additional details to follow!

Read More ...

22 MayCentral Valley Expressway at Dusk

This beautiful photograph looks north at the Central Valley Expressway with Squaw Butte in the background. Thank you to Dave Butzier & Idaho Airships for providing the Central Valley Expressway Coalition with this image.

Read More ...

11 JanCentral Valley Expressway Progress Update

A photo looking southwest at the south end of the project.  Chinden Boulevard to the left edge of the photo.

The following aerial photos detailing the progress of the Central Valley Expressway (Highway 16 Extension Project) were taken Fall 2013.  Thank you to Dave Butzier & Idaho Airships for providing these beautiful photographs to the Central Valley Expressway Coalition.            

Read More ...

18 AugCentral Valley Expressway Construction Update

sh 16 boise river bridge construction 7_18_13 003

The following photos show the progress, to date, on the Central Valley Expressway (Highway 16 Extension).  Thank you to Dave Butzier & Idaho Airships for providing the photographs to the Central Valley Expressway Coalition.        

Read More ...

12 JunCVE Construction Photo Tour

The following photographs were taken during a recent tour of the progress on the Central Valley Expressway (Highway 16).                       All photos by Matthew May and  © Central Valley Expressway Coalition, LLC

Read More ...

18 MayBoise River Bridge

This photo, taken on May 1st, 2013, shows the Boise River Bridge. The Northern portion of the bridge is to the right and the Southern portion is to the left. There are four remaining spans that still need girders (spans 1-4).  Those girders will be set the first week of June.  77 of the 121 [...]

Read More ...

19 FebCVE Construction Update

All photographs taken on February 6th, 2013. SH-16, the Boise River Bridge looking north at Spans 5, 6, 7 & 8.  The closest span, Span 5 crosses the Boise River low flow channel. SH-16, the Boise River Bridge looking south from Abutment No. 2 at the north end, looking toward Span 8. SH-16, the Phyllis [...]

Read More ...

03 FebCVE Construction Update

This photo, taken on January 16th, shows the size of the girders being set for the bridge.  Each girder is 157 feet long and 7’1″ deep. The first 33 girders have been set, covering three spans.  The final bridge will consist of 11 spans and 121 girders. This photo, also taken on January 16th, shows [...]

Read More ...

12 JanGirders Arrive

The girders have begun to arrive for the Boise River Bridge.  The photo at the left shows an aerial view of the girders traveling to the site.  Each girder is 157 feet long and 6 feet deep. The first two girders were set on Monday, January 7th.  Six more girders were set on Wednesday, January [...]

Read More ...

22 DecCVE Aerial Photos

The first photograph looks north along the SH-16 alignment from the Phyllis Canal/Joplin Road area toward the Boise River Bridge and SH-44 in the distance. November 29th, 2012 The second photograph looks south from SH-44 at the SH-16 alignment showing the Boise River Crossing and Phyllis Canal in the distance. November 29th, 2012 The third photograph shows [...]

Read More ...