Monthly Archives: February 2013

19 FebCVE Construction Update

All photographs taken on February 6th, 2013. SH-16, the Boise River Bridge looking north at Spans 5, 6, 7 & 8.  The closest span, Span 5 crosses the Boise River low flow channel. SH-16, the Boise River Bridge looking south from Abutment No. 2 at the north end, looking toward Span 8. SH-16, the Phyllis [...]

Read More ...

03 FebCVE Construction Update

This photo, taken on January 16th, shows the size of the girders being set for the bridge.  Each girder is 157 feet long and 7’1″ deep. The first 33 girders have been set, covering three spans.  The final bridge will consist of 11 spans and 121 girders. This photo, also taken on January 16th, shows [...]

Read More ...