18 MayBoise River Bridge

This photo, taken on May 1st, 2013, shows the Boise River Bridge. The Northern portion of the bridge is to the right and the Southern portion is to the left.

There are four remaining spans that still need girders (spans 1-4).  Those girders will be set the first week of June.  77 of the 121 girders have been set in this photo, as well as the first three concrete deck placements.

Projected completion date: Summer 2014